Module 04 / Lesson 4.9 · Review candidate

Investigate discrepancies and manage changes

Keep failed checks, corrective work and re-verification traceable.

2.0 minutes · English captions · Illustrations and worked example

This lesson’s core explanations and worked-example reasoning are narrated. The table restates the example for reference; the practice activity and model answer are reading exercises.

English captions available.

Read the lesson · Download captions · Download transcript

Narration and visual explanations

Open View Technical Explanation to see each diagram, its text description and the matching narration. Standard abbreviations and numerals are used visually.

Part 1 of 4

Describe the mismatch

View Technical Explanation · Diagram 1
Describe the mismatch — diagram 1. Description below.
Required model A and observed model B form a recorded mismatch, with impact still to be assessed. Key points: Required valve model A; Observed valve model B; Affected function identified.

Lesson explanation

The accepted schedule specifies valve model A, while the installed plate shows model B. Record the mismatch and its exact location. Do not decide from the model number alone whether the difference is harmless. Assess relevant materials, connection, cleaning and functional implications with the responsible experts. Retain the original observation even if the supplier later replaces the valve.

Part 2 of 4

Choose a controlled action

View Technical Explanation · Diagram 2
Choose a controlled action — diagram 2. Description below.
A finding branches into correction or authorized change, then returns to defined verification. Key points: Investigate cause and impact; Correct or assess change; Define verification.

Lesson explanation

Correction may restore the specified valve, or a proposed design change may require an authorized assessment. These are not the same route. Do not revise the acceptance criterion merely to match what arrived. Define what verification follows the approved action and whether earlier checks or later tests are affected. Keep the decision and supporting rationale linked to the finding.

Part 3 of 4

Verify closure evidence

View Technical Explanation · Diagram 3
Verify closure evidence — diagram 3. Description below.
Action completion and reinspection feed a reviewed closure decision; ordering a part alone leaves the finding open. Key points: Action completed; Applicable reinspection; Reviewed conclusion.

Lesson explanation

A purchase order for the replacement is not closure evidence. After the authorized action, obtain the specified installation evidence and assess any related implications. Retain the original failure and the subsequent result as separate records. A clean second result should not erase the history or imply that the first configuration had always complied.

Part 4 of 4

Limit conditional progression

View Technical Explanation · Diagram 4
Limit conditional progression — diagram 4. Description below.
The open finding limits affected tests; a separate next-stage activity needs its own assessed and authorized basis. Key points: Defined next activity; No significant impact basis; Responsible authorization.

Lesson explanation

Annex 15 permits conditional approval to proceed to the next qualification stage following a documented assessment that there is no significant impact on the next activity. Responsible authorization is still needed. For example, an unresolved gasket issue may prevent wetted-system challenges even if a separately assessed dry control-display check could proceed. This activity-specific dry-check example is a practical teaching recommendation, not wording prescribed by the Annex or permission to proceed. Do not use a high completion percentage as a substitute for the assessment.

Worked example

Fictional worked example — not an approved site record
EventStatus
Wrong valve observedDeviation recorded and impact assessed
Replacement orderedAction planned; finding still open
Replacement verifiedClosure evidence available for review
Next-stage activitySeparate documented authorization required

Apply it · Activity 9

Draft a discrepancy entry for the wrong valve and identify what is required before closure or limited progression.

Open workbook activity
Compare with model reasoning

Record expected/actual model and evidence, assess impact, use the controlled correction/change route, define reinspection and retain history. Any limited OQ progression needs an activity-specific no-significant-impact assessment and authorization.

Knowledge check

1. The replacement valve has been ordered. Is the installation finding closed?

Technical sources