Apply the DQ reasoning
20 distinct application questions. This open-book self-study assessment exposes its answer key in the source and below. The suggested practice target is 85% (17/20), not a regulatory threshold, DQ acceptance rule or proof of independent competence. Unanswered questions must be completed before scoring. Answers are not sent to a server.
Answer key and explanations
1. Proposed design suitability was evaluated within the stated scope — Limit the conclusion to the evidence and scope of the design review.
2. Assess the changed requirements and reconcile the review baseline — A revision change can alter the design-review basis.
3. Suitability across the intended operating volume range — Supplier capability cannot define the missing process need.
4. ±0.6 °C; exceeds the illustrative ±0.5 °C requirement — The aligned worst-case sum is ±0.6 °C, exceeding the fictional ±0.5 °C requirement. It does not support the requirement and is not a complete uncertainty budget.
5. The 0.4 °C sum supports review, subject to applicable conditions — The conservative sum is within the teaching limit, but conditions and later verification remain relevant.
6. Request gasket evidence relevant to product and cleaning exposure — Identity is necessary evidence but does not alone prove suitability.
7. Reference the reviewed revision and retain later cleaning verification — The closure needs reviewed evidence and must retain future verification obligations.
8. Whether shared failures undermine the proposed protection — Evaluate the failure mechanism rather than counting devices or labels.
9. Define justified recovery behaviour and link it to later verification — Recovery can affect risk and must be addressed as relevant to intended use.
10. An access feature whose adequacy still requires further assessment — A login feature does not establish full access, record or computerized-system compliance.
11. Maintenance access in the final installed arrangement — Review access with the relevant installed configuration and dimensions.
12. A comparison of utility supply conditions with vessel design needs — System qualification does not automatically establish interface compatibility.
13. Keep the finding unresolved until suitable evidence is reviewed — Ownership and schedule are management information, not evidence of effectiveness.
14. Examine severity, uncertainty and the proposed control evidence — A score alone cannot settle an unsupported high-consequence scenario.
15. Arrange site suitability review and a justified verification supplement — The site must assess protocol suitability and coverage of relevant verification needs.
16. Does the tested configuration and function remain applicable after change? — Evidence reuse depends on applicable configuration, conditions and impacts, not presentation.
17. Retain the prior baseline and reassess affected design conclusions — Controlled history and impact review allow the decision to be reconstructed.
18. Progress after documented impact assessment and stage authorization — Progression is specific to the proposed activity and does not close the design finding.
19. 80% coverage; no percentage establishes design suitability — 8/10 × 100 = 80%; this does not establish suitability or a release threshold.
20. Controlled baseline, open findings and planned verification dependencies — IQ needs the accepted design basis and visibility of unresolved dependencies.